On 5th January 2017, construction work began at the Provincial Complex Hospital named after L. Rydygier in Toruń. The commencement of works was marked by a formal ground-breaking ceremony attended by representatives from the regional authorities, the contractor, the investor, the hospital management, and patients themselves. Although preparations for this stage have been underway for almost a month, as the construction site was officially handed over earlier, extensive preliminary work was required, including tree felling and demolition. Groundworks have commenced, preceded by meticulous planning regarding the sequence of works on the hospital grounds, as well as the establishment of traffic routes and the minimisation of disruption for staff and patients.
The first project to be completed is the multi-level car park – designed to quickly resolve the parking issues on the hospital site. It is expected to be ready by the end of the third quarter of this year. Simultaneously, construction of Building H is planned, which will house the emergency department, a landing pad for medical helicopters, and a central operating block, while construction of the administrative building is scheduled to begin in spring 2017.
At the same time, design work will continue on the existing hospital building. Concurrently, work will also be carried out on the construction of technical facilities, including a boiler room, rainwater tanks, retention tanks, a new substation, and the refurbishment and expansion of all utility connections.
Preparations will be carried out and construction of the infectious diseases and psychiatric hospital buildings will begin, even while Building H is still under construction. This will be preceded by the demolition of existing technical buildings on the hospital site.
The construction work is scheduled to be completed by the end of 2019. Tenders for equipping the hospital will be conducted during the construction process – some elements must be installed during the building phase or during finishing works, such as surgical columns and medical gas installations. Further equipping and outfitting of the hospital are planned for the coming months.