Kujawsko-Pomorskie Inwestycje Medyczne Sp. z o.o. are analysing bids in the tender for the reconstruction and modernisation of the network at the psychiatric hospital in Świecie. Three companies submitted bids in the tender.
The term “networks” in this context refers to all the key functions essential to the hospital’s operations concerning the supply of utilities: electricity, water, sanitation, data transmission, and stormwater drainage.
The tender covered eight tasks:
- The project involves the reconstruction of the sanitary drainage system, including the replacement of any surfacing that is damaged during the reconstruction process. The existing drainage system has deteriorated due to prolonged use – the hospital has been operating since 1855, and the current network, despite previous upgrades, no longer meets the safety standards required by law. A new drainage system utilising PVC pipes has been designed, to collect wastewater from the existing buildings, along with concrete inspection chambers, which will replace the current infrastructure.
- A complete overhaul of the water network, alongside the modernisation of the retention reservoir, which, in the event of a disruption to the municipal water supply, must provide water to the hospital for a period of 12 hours. The existing water network will be disconnected and sealed. A completely new network will take over its function, with the existing water reservoir – currently supplied by the municipal water grid – serving as its primary source.
- The second phase of the rainwater drainage system is underway. The first phase was completed in 2014. The system will collect rainwater from the hospital grounds and channel it into the municipal sewer network. As part of this rainwater drainage project, a two-chamber retention tank will also be constructed, designed to protect the hospital from the effects of heavy rainfall. Excess water will be temporarily stored in the tank before being directed to a stormwater pumping station, and from there, to the municipal sewer system.
- The refurbishment of the existing distribution network, which has suffered from degradation over the years, is underway. For the upgraded distribution network, two power supply routes have been planned: a primary ring system and a linear system for standby power. Cable connection points for both lines are provided at each building. All cabling will be replaced with copper wiring. The existing overhead low-voltage distribution network will be decommissioned, and its function will be taken over by an underground network. Furthermore, main fire isolation switches have been planned for each building.
- The external lighting system across the site will be upgraded – some of the existing lighting and associated infrastructure will be removed, and new steel poles and aluminium LED luminaires will be installed.
- The fibre optic network upgrade – the inter-building fibre optic cabling – will be installed within the telecommunications ducting. The layout will be in a star configuration, with the administration building serving as its central point. This will significantly improve communication between the hospital’s numerous buildings.
- The refurbishment of the telecommunications infrastructure, including the installation of cable ducts and the laying of cable piping made from PVC.
- Monitoring of the substation, including the generator room – installation and commissioning of the monitoring system.
It is estimated that the works will cost approximately 11 million złoty. These costs will be borne by both KPIM, through the EBI 2 credit line, and the Hospital, which is actively seeking investment support from the Regional Fund for Environmental Protection and the European Regional Development Fund (ERDF), under activity 2.1 of the Regional Operational Programme for the Wielkopolska region (WK-P) for the period 2014-2020, focusing on e-health.
It is anticipated that the entire project will be completed in the first half of 2020.