On 19 March 2019, KPIM and the consortium of companies Elektrobud Grudziądz and Melbud SA signed an agreement to undertake eight projects as part of the redevelopment and modernisation of infrastructure at the Regional Hospital for Neurological and Psychiatric Patients in Świecie. In this instance, “infrastructure” refers to all key areas essential to the hospital’s operations, including the supply of electricity, water, sanitation, data transmission, and stormwater drainage.
The total cost of the project is estimated at approximately 11 million Polish zloty. These costs will be borne by both KPIM, through the EBI Line 2 credit facility, and the Hospital, which is actively seeking investment support from the Regional Fund for Environmental Protection and the European Regional Development Fund (ERDF), under Activity 2.1 of the Regional Operational Programme for the Wielkopolska Region (WK-P) for the period 2014-2020.
The consortium will undertake the following tasks (a more detailed description of the activities can be found). here):
- Refurbishment of the sanitary sewer system, including the reinstatement of any surfacing that is damaged during the works.
- Complete refurbishment of the water supply network, including modernisation of the retention basin, and reinstatement of the surfacing.
- Second phase of the rainwater drainage system construction.
- Reconstruction of 0.4 kV distribution network infrastructure.
- Refurbishment of the external lighting system across the site.
- Optical fibre network upgrade.
- Refurbishment of the telecommunications infrastructure.
- Monitoring of a substation with a generator set.
The contractor has until the end of July 2020 to complete the works as agreed.