Technical acceptance tests for the passenger lift in Block A at the Kuyavian-Pomeranian Centre for Pulmonology are nearing completion.
Construction work has now been completed, and the final acceptance procedures are also underway. Currently, the contractor is awaiting the occupancy permit, and the crane is expected to be handed over to the user before the end of this week.
The lift was designed to serve the hospital administration, as well as to facilitate access to storage rooms created in the former medical sterilisation unit.
As the lift shaft runs within the building, it was necessary to adapt existing spaces for its installation. Consequently, some of these spaces have been repurposed, changing from medical facilities to office areas. As a result, the doctor’s office and diagnostic room have been relocated. Building A now provides medical services on the ground and first floors, technical facilities on the ground floor, and storage space in the basement.
The project was extended due to the outbreak of the pandemic and lasted slightly over six months. The total cost of the undertaking was over 500,000 zł.
This is not the final investment planned for KPCP this year. Currently, a tendering process is underway for the second phase of the refurbishment and expansion of the healthcare facility.