Final preparations are underway to initiate the investor acceptance process for building number 7 at the Provincial Specialist Hospital named after Father J. Popiełuszko in Włocław.
The building is undergoing final sanitary, epidemiological, and fire safety inspections. The contractor is awaiting feedback from the Public Health Authority (Sanepid) and the State Fire Service before the acceptance procedure can begin.
Building number 7 previously housed a respiratory ward, specifically the Department of Pulmonology, Diagnostics, and Treatment of Lung Cancer. It is one of the older buildings within the hospital complex. Initially, the original new hospital project had designated it for demolition; however, following expert assessments, it was determined suitable for renovation and reconstruction. The current state of the building represents the culmination of these efforts: it is modern, well-connected to the rest of the hospital complex, yet retains a degree of seclusion, allowing for a peaceful recovery and rehabilitation environment. This was precisely the aim of the renovation and reconstruction – to create a facility for both inpatient and outpatient rehabilitation services. The planned rehabilitation clinic and outpatient rehabilitation services will be located on the ground floor. The upper floors, accommodating a total of 40 beds, have been designated for inpatient rehabilitation wards specialising in general medicine, neurology, and cardiology. This will allow patients, after treatment on the neurology, cardiology, and internal medicine wards, to undergo rehabilitation in a quieter environment, away from the pressures of the wards where they received care during their most critical periods.
Tenders are currently being prepared for medical and non-medical equipment and furnishings for buildings number 7 and 12.
Building number 7 is the final of three buildings undergoing renovation, a project that began in 2017 as part of a single investment undertaking. Previously, the administrative buildings numbered 9 and 12 were completed. Building 12 will temporarily function as a transitional ward, utilised by various departments during the ongoing expansion and renovation phases of the hospital, and is ultimately intended to become a geriatric ward.
The total cost of the construction work on buildings 7 and 12 is almost 13 million złoty.