In the presence of the Marshal of the Kuyavian-Pomeranian Voivodeship, Piotr Calbecki, the Presis On 2 December 2016, Aleksander Szczęsny, representing Kujawsko-Pomorskie Inwestycje Medyczne, signed a handover protocol for the construction site, together with the project engineer, hospital management, and representatives of the main contractor. The necessary formal procedures have now been completed, paving the way for investment to begin at the Provincial Hospital Complex named after L. Rydygier in Toruń.
According to current plans, the expansion and refurbishment project is expected to take 36 months. The hospital’s total floor space will increase from 20,000 to over 50,000 square metres, including areas for the psychiatric and infectious diseases hospitals after their relocation to Bielany. The expanded hospital will accommodate 983 beds (again, including beds in the infectious diseases and psychiatric departments) and will become a comprehensive hospital complex featuring modern diagnostic facilities, patient wards, an operating block, and an emergency department. It will also include the aforementioned infectious diseases and psychiatric hospitals, located in separate buildings surrounded by greenery and connected to the main building via walkways. A helipad has been designed on the roof of the main building, above the emergency department, to reduce the time it takes to transfer patients from helicopters to the emergency area.
The construction work will cost 336 million złoty, while further expenditure on equipment for the hospital complex is estimated at nearly 200 million złoty.